We have looked into this in NJ the Rough costs would be as follows: 500k for the building 500k for the turf or surface 500k - 1 million dollars for the land and grading 250k for COAH (this maybe a NJ specific cost) 250k - 500k for an environmental study 2 million to 3 million for the total project.